Jay & Jay Industries was contracted by Arcadia Energy to consult and design on a secondary containment area and emergency response products around a vehicle refuelling station for council approval. Once Council had approved all aspects of the plan Jay & Jay Industries was again selected to carry out the installation and training of staff.
Work was carried out in compliance with Site safety management plans, as Sub contractor to the head contract. Jay & Jay Industries were required to undertake this sensitive project in full view of the public. Design and Installation was made more complex as existing concrete pads required epoxy treatment to insure a water tight seal on all bunding.
Date: October 2014
Location: Logan City, Queensland, Australia
Features Summary
Materials:
Design:
Completed in 5 stages covering Design & Methodology, Supply of goods, Installation of section A, Leak testing after cure, Installation of Sediment control devices for ready deployment on Storm water drains, Toolbox training of staff and implementation of housekeeping guidelines.